Central heating, high
load capacity floors, central fire protection system, electronic security
system, property management
Zoning Permit:
04.97
Construction Permit:
04.97
Construction Start:
05.97
Construction Complete:
11.97
Number of Floors:
Two above ground
Gross Building Area:
1 500 m2
Lease Area:
1 200 m2
Garage Parking:
street
Occupancy:
100%
On behalf of Apmart s.r.o.,
Landmark secured the purchase of an empty two level building located on
845 m2 of land in October 1996. Landmark’s development scheme was to renovate
this abandoned spice facility into a modern warehouse storing textiles/goods
on the ground floor and on the first floor a showroom displaying goods
and office space for company’s staff.
Despite years of neglect,
the 90-year-old building was in relative good condition and so it was determined
to reconstruct the building. Plans and documents were submitted for zoning
and construction approval, which was granted within three months. Reconstruction
started immediately with occupancy occurring in November 1997. The graceful
industrial architectural character of the building was maintained and stands
as an excellent example of the Holešovice’s past.